Hammond, LA

Target
Screen Shot 2022-06-21 at 11.21.26 AM

General Project Scope

  •  Manufacturer: Sika Sarnafil
  • 60Mil PVC mechanically fastened
  • Installed edge metal (Rhinobond Roofing) 1500 squares
  • Installed new walkpads and pipe supports


Logistical Challenges

The biggest logistical challenge with this contract was making sure we did not interfere with Target's normal operations, while also keeping the shoppers safe. We did this by keeping the work area small, clean, and away from the parking lot.