RYCARS was contracted to install a new GAF SBS roof system for the canopy along with the scope of work below.
Scope of work:
- asbestos abatement of the canopy roof and columns
- installed new conduit, wiring and LED light fixtures
- removed existing transformers, conduit and conductors
- painted the canopy columns and underside
- cleaned roof drains
- installed sheet metal trims and flashing
- concrete repair and steel reinforcement at various columns
- painted the walkway (canopy, structure and roof) and mansard at the station building, admin building and engineering building.
Our team (including subs) worked at night to ensure that normal business operations of this active train station could continue undisturbed. RYCARS worked with Amtrak engineering, station staff and watchmen to successfully complete the project.